Resource Acquisition
The IESO is engaging on the proposed Long Lead-Time Request for Proposals (LLT RFP). This procurement is part of the IESO’s broader Resource Adequacy Framework – an enduring approach to identifying the type of acquisition activity to use to resolve system needs. The framework contemplates a multi-pronged approach to secure resources, generally based on the length of the contract term.
The LLT RFP engagement plan outlines the objectives, approach, timeline and considerations for engaging stakeholders and conducting outreach to other targeted audiences throughout the development of the procurement This engagement plan may be subject to review and updates as the process evolves.
All comments and enquiries on this engagement can be directed to engagement@ieso.ca.
Learn more about engagement opportunities for Indigenous Communities and Municipalities.
Date | Agenda Item | Action |
---|---|---|
October 21, 2025 |
Engagement Webinar The IESO will provide updates to the design of the LLT RFP and discuss feedback received to date. |
|
October 20, 2025 |
Repowering Existing Facilities Webinar The IESO will discuss eligibility considerations regarding expansions and upgrades of energy resources to inform eligibility across the suite of IESO procurements. |
|
September 30, 2025 |
Feedback due following the September 16 webinar. Feedback Received: |
|
September 16, 2025 |
The IESO will discuss updates to the design of the LLT RFP based on feedback received to date and next steps. |
This webinar was presented during the IESO's September stakeholder engagement sessions, see full agenda for more information. |
August 19, 2025 |
||
June 17, 2025 |
Feedback due following the June 5th webinar. Feedback Received: August 14, 2025: IESO Response to Feedback |
|
June 5, 2025 |
Engagement Webinar The IESO will discuss updates to the design of the LLT RFP based on feedback received to date and next steps. |
|
May 9, 2025 |
Feedback due following the April 23rd webinar. Feedback Received: June 13, 2025: IESO Response to Feedback |
|
April 23, 2025 |
Engagement Webinar The IESO will share insights from the RFI responses and discuss considerations related to the design of a long lead time resource procurement to help inform the report back to the Minister of Energy and Mines. |