Forecasting and Planning
Regional electricity planning has kicked-off in the GTA West electrical region to ensure a reliable supply of electricity, and to support local growth and economic development. Regional planning looks at the unique needs of each region, and considers wire and non-wire options and innovative resources to meet the needs. This engagement initiative will provide interested parties with an opportunity to offer input for consideration during the regional planning process.
Regional electricity plans take up to a 20-year outlook on every region in the province. The planning process provides an opportunity for participants to tell the IESO about anticipated needs and priorities, and to contribute to the development of the options for meeting this region’s future electricity needs.
All interested parties are invited to participate in this engagement initiative and may include but are not limited to:
All comments and enquiries on this engagement can be directed to engagement@ieso.ca.
GTA West Working Group - The Technical Working Group is lead by the IESO, and consists of the LDCs in the region and the local transmitter. The group will use regional planning engagement initiatives to incorporate input while developing the IRRPs for the region.
All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.
Also see the regional planning webpage for GTA West
Date | Materials | Expected Actions |
---|---|---|
June 23, 2025 |
Deadline for comment on June 2 webinar. Feedback Received: |
|
June 2, 2025 |
Public Webinar #1: Draft Forecasts
|
|
November 28, 2024 |
Final GTA West Scoping Assessment Outcome Report and the IESO’s response to feedback |
|
November 14, 2024 |
Deadline for public comment Feedback Received: |
Posted feedback received |
October 29, 2024 |
Public Webinar |
|
October 24, 2024 |
Draft report posted for public feedback |
|
October 9, 2024 |
Launch Scoping Assessment Engagement |
|
Date | Materials | Expected Actions |
---|---|---|
July 15, 2021 |
Final GTA West IRRP |
|
May 20, 2021 |
Feedback on Public webinar #3 due |
Posted |
May 6, 2021 |
Public webinar #3
|
Seek input on IRRP recommendations
|
September 17, 2020 |
Posted |
|
August 26, 2020 |
Feedback on public webinar #2 due |
Feedback posted |
August 5, 2020
|
Public webinar #2
Outline of next steps, timelines and considerations for broader engagement |
Recorded Presentation
|
April 17, 2020 |
Posted |
|
March 26, 2020 |
Feedback on public webinar #1 due |
Feedback posted |
March 12, 2020
|
Public webinar #1
Summary of preliminary regional demand forecast and needs and draft engagement plan |
Presentation and recorded webinar posted Seek input on draft engagement plan, electricity demand forecast and preliminary needs identified |
February 20, 2020 |
Launch GTA West IRRP engagement initiative
|
|
August 8, 2019
|
Final GTA West Scoping Assessment Outcome Report
|
Final version posted following a two-week comment period |
August 8, 2019 |
GTA West Scoping Assessment Outcome Report – IESO responses to Public Comments |
|
July 8, 2019 |
Deadline for public comment on draft GTA West Scoping Assessment Outcome Report
|
|
June 24, 2019
|
Public webinar Presentation
|
Webinar recording Seek input on draft Scoping Assessment Outcome Report
|
June 20, 2019
|
Draft GTA West Scoping Assessment Outcome Report
|
Draft posted for public comment |
June 6, 2019 |
Launch GTA West Scoping Assessment engagement
|
|