Stage 1 - Prepare application
Contact your transmitter or distributor for questions about this stage of the process. |
Your organization will want to take the following preliminary steps to lay the groundwork for your application to connect your new or modified facility to Ontario's electricity system.
- Identify the connection point(s) and preliminary design requirements of the new or modified connection facility by contacting the owner of the system or facility you intend to connect to
This could be the:
- Distributor who owns the local distribution system
- Transmitter who owns the transmission system
- Facility owner, if you're seeking to connect within an existing facility that belongs to a customer of a transmitter or a distributor. The facility owner (the "host") is, in turn, responsible for contacting their transmitter or distributor on your behalf.
Transmission system operates at voltage levels >50 kV Distribution system operates at voltage levels < 50 kV |
- Confirm the connection assessment processes that apply to your new or modified facility and who is responsible to initiate them
Connection type | Required processes and parties responsible |
---|---|
New or modified connection of less than or equal to 10 MW to distribution system or to an existing load or generation facility within a distribution system |
Distributor's connection impact assessment process |
New or modified connection larger than 10 MW to a distribution system or to an existing load or generation facility within a distribution system
|
Distributor’s connection impact assessment process
The distributor is responsible for initiating the IESO's and transmitter's connection assessments process on your behalf
|
New or modified connection to a transmission system
|
IESO’s and transmitter’s connection assessments process
Your organization is responsible for initiating the IESO's and transmitter's connection assessments process
|
New connection within an existing load or generation facility that is connected to a transmission system
|
IESO’s and transmitter’s connection assessments process
Your host is responsible for initiating the IESO's and transmitter's connection assessments process on your behalf |
If your new or modified connection doesn’t fall into any of the categories listed above, please contact the IESO or consult Market Manual 1.4 for support.
- Collect the technical data required to prepare the application
To streamline the initiation of their connection assessments processes, the IESO and Hydro One have developed joint system impact assessment (SIA) and customer impact assessment (CIA) application forms for generation (including electricity storage), renewable generation and load projects.
If you are required to participate in the IESO's and the transmitter's connection assessments process, your complete application must be sent via email to IESO and Hydro One at the addresses indicated on the front page of the form.
Please visit the Obtain Conditional Approval to Connect webpage for the applicable forms.
You may contact the IESO for any questions you have about completing the SIA application forms, or if your transmitter is not Hydro One Networks Inc. or Hydro One Sault Ste. Marie.
If your facility is required to participate in a distributor's connection assessment process, contact the distributor for further instructions.