Final Integrated Regional Resource Plan for the Hamilton sub-region posted

February 28, 2019

Power system capacity and reliability requirements, and recommendations to meet them over the next 20 years, are the focus of the Hamilton sub-region’s latest Integrated Regional Resource Plan

Now available online, this IRRP is the outcome of a regional planning cycle, initiated following the completion of a needs assessment for the area. This included the creation of a technical working group, composed of Alectra Utilities, Hydro One Networks Inc. and the IESO, as well as a regional engagement for input into the creation of a Scoping Assessment Outcome report.