Technical Requirements for Large Computational Loads Connecting to the Ontario Power System

Operations

This page is dedicated to the Independent Electricity System Operator’s (IESO) Technical Requirements for Large Computational Loads Connecting to the Ontario Power System initiative.

The IESO has identified a clear gap on the existing technical performance requirements in the Market Rules for the integration of large computational loads such as artificial intelligence (AI) facilities and cryptocurrency facilities. In response, the IESO has developed new technical requirements to address the gaps and is initiating a stakeholder engagement to share the proposed requirements, gather feedback, and discuss any concerns with all stakeholders.

The document posted includes both new and existing technical requirements to give the stakeholders a whole picture of the technical requirements needed for connecting a large computational load in Ontario power system. After the stakeholder engagement is completed, the IESO will update the new requirements into the Market Rules or relevant Market Manuals.

For questions or feedback please contact engagement@ieso.ca.

Schedule of Activities

Date

Agenda Item

Actions

June 18, 2026

Public engagement webinar.

June 17, 2026

Consolidated written feedback posted.

June 3-17, 2026

One-on-one sessions to be held as needed by the IESO to discuss comments.

May 28, 2026

Deadline for feedback.

May 4-28, 2026

Open call for one-on-one sessions with interested stakeholders.

Interested stakeholders are asked to contact engagement@ieso.ca by May 28, 2026.

May 1, 2026

IESO seeking stakeholder review and feedback.

Stakeholders are asked to submit their feedback using the provided feedback form to engagement@ieso.ca by May 28, 2026.