Regional planning for the Kitchener-Waterloo-Cambridge-Guelph (KWCG) region was completed in July 2026. This engagement initiative provided Indigenous communities, municipalities, customers and interested parties with an opportunity to offer input for consideration into the development of the 2026 KWCG Integrated Regional Resource Plan (IRRP).
All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.
See also the regional planning webpage for Kitchener/Waterloo/Cambridge/Guelph
2026 KWCG Integrated Regional Resource Plan (IRRP)
2024 KWCG Scoping Assessment Outcome Report
2024 KWCG Needs Assessment Report – Hydro One
2019 KWCG Scoping Assessment Outcome Report and Terms of Reference
| Date | Materials | Expected Actions |
|---|---|---|
|
July 8, 2026 |
KWCG electricity plan posted |
|
|
June 24, 2026 |
Deadline for public comment on Public Webinar #4 regarding options analysis and draft recommendations to address remaining needs Feedback received: |
All feedback posted |
|
June 10, 2026 |
Public Webinar #4: Draft Integrated Regional Resource Plan (IRRP) recommendations |
|
|
January 6, 2026 |
||
|
October 21, 2025 |
Deadline for public comment on Public Webinar #3 regarding remaining needs and screening options analysis Feedback received: |
Posted |
|
September 29, 2025 |
Deadline for public comment on Public Webinar #3 regarding draft recommendations to address priority needs |
|
|
September 23, 2025 |
Public Webinar #3: Addressing Priority Needs and Identifying Remaining Needs |
|
|
August 19, 2025 |
||
|
June 17, 2025 |
Deadline for public comment on Public Webinar #2 Feedback Received: |
Posted |
|
May 27, 2025 |
Public Webinar #2: |
|
|
April 8, 2025 |
||
|
January 8, 2025 |
Deadline for public comment on Public Webinar #1 Feedback Received: |
Posted |
|
December 12, 2024 |
Public Webinar #1: Draft forecast |
|
|
July 8, 2024 |
||
|
July 2, 2024 |
Deadline for public comment on the draft KWCG Scoping Assessment Outcome Report Feedback Received: |
All feedback posted |
|
June 17, 2024 |
Public Webinar |
|
|
June 11, 2024 |
Draft posted for public feedback |
|
|
June 3, 2024 |
Launch KWCG Scoping Assessment Engagement |
| Date | Materials | Expected Actions |
|---|---|---|
|
May 6, 2021 |
Final KWCG IRRP |
Engagement closed |
|
April 1, 2021 |
Feedback on public webinar #2 due |
|
|
March 18, 2021 |
Public webinar #2
|
Seek input on further discussions needed to initiate near-term projects |
|
September 2020 |
Status update
|
|
|
January 29, 2020 |
Response posted |
|
|
December 19, 2019 |
Feedback on public webinar #1 due
|
Feedback posted |
|
December 5, 2019 |
Public webinar #1 Presentation
Summary of preliminary regional demand forecast and needs and draft engagement plan |
Recorded Presentation Presentation and recorded webinar posted Seek input on draft engagement plan, electricity demand forecast and preliminary needs identified |
|
November 21, 2019 |
Engagement plan posted for review and comment |
Posted |
|
May 9, 2019 |
Final KWCG Scoping Assessment Outcome Report and Terms of Reference
|
Final version posted following a two-week comment period |
|
May 9, 2019 |
KWCG Scoping Assessment Outcome Report and Terms of Reference – Responses to Public Comments |
Posted |
|
April 25, 2019 |
Deadline for public comment on draft KWCG Scoping Assessment Outcome Report and Terms of Reference
|
Posted |
|
April 11, 2019 |
Draft KWCG Scoping Assessment Outcome Report and Terms of Reference
|
Draft posted for public comment |