Regional planning for the Burlington to Nanticoke electrical region was completed in November 2024. This engagement initiative provided communities and stakeholders with an opportunity to offer input for consideration into the development of the 2024 Burlington to Nanticoke Integrated Regional Resource Plan. A Regional Infrastructure Plan (RIP) led by Hydro One will be initiated next, as part of the regional planning process. The ongoing Kitchener, Waterloo, Cambridge and Guelph electricity plan will determine the end point of the new lines and stations from Brant/Powerline station to Middleport-Detweiler circuits. Lastly, the Hamilton addendum will kick-off in 2025 with updates being shared on this webpage.
Regional planning looks at the unique needs of each region, and considers a range of options to meet the area’s needs over a 20-year period. Based on emerging electricity needs identified in this current cycle, a comprehensive planning approach to develop an Integrated Regional Resource Plan (IRRP) is underway that will examine the Brant, Hamilton and Caledonia-Norfolk sub-regions.
We welcome your input on all aspects of this process, including anticipated community needs and priorities, and potential options for meeting this region’s future electricity needs. All interested parties are invited to participate in upcoming engagement initiatives, including but not limited to:
Technical Working Group - The Technical Working Group is lead by the IESO, and consists of the LDCs in the region and the local transmitter. The group will use regional planning engagement initiatives to incorporate input while developing the IRRPs for the region.
All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.
2024 Burlington to Nanticoke Integrated Regional Resource Plan (IRRP)
2022 Burlington to Nanticoke Scoping Assessment Outcome Report
2019 Hamilton Integrated Regional Resource Plan (IRRP)
2017 Burlington to Nanticoke Scoping Assessment Outcome Report
2014 Burlington to Nanticoke Scoping Assessment Outcome Report
See also the regional planning webpage for Burlington to Nanticoke
Date | Materials | Expected Actions |
---|---|---|
November 28, 2024 |
Burlington to Nanticoke Electricity Plan posted |
Engagement closed |
November 7, 2024 |
Deadline for public comment on Public Webinar #3 Feedback Received: |
All feedback posted |
October 24, 2024 |
Public webinar |
|
August 21, 2024 |
Posted |
|
July 16, 2024 |
Deadline for public comment on Public Webinar #2 Feedback Received: |
All feedback posted |
June 25, 2024 |
Public Webinar #2 |
|
November 7, 2023 |
||
October 2, 2023 |
Deadline for public comment on Public Webinar #1 Feedback Received: |
Posted |
September 11, 2023 |
Public Webinar #1 Draft Engagement Plans: Draft Burlington to Nanticoke Region Electricity Demand Forecast Presentation: Overview of preliminary regional demand forecast and needs and draft engagement plan. |
|
December 5, 2022 |
Final Burlington to Nanticoke Scoping Assessment Outcome Report |
Final version posted |
November 24, 2022 |
Deadline for public comment on draft Burlington to Nanticoke Scoping Assessment Outcome Report No feedback received |
All feedback posted |
November 10, 2022 |
Public webinar
|
|
November 3, 2022 |
Draft Burlington to Nanticoke Scoping Assessment Outcome Report |
Draft posted for public comment |
October 27, 2022 |
Launch Burlington to Nanticoke Scoping Assessment engagement |