Forecasting and Planning
Regional electricity planning is underway for the Peterborough to Kingston electrical region to ensure a reliable supply of electricity, and to support local growth and economic development. Regional planning looks at the unique needs of each region and considers wire and non-wire options and innovative resources to meet the needs. This engagement initiative will provide interested parties with an opportunity to offer input for consideration during the regional planning process.
Regional electricity plans take a 20-year outlook on every region in the province. The planning process provides an opportunity for communities to inform the IESO about anticipated needs and priorities, and to contribute to the development of the options for meeting this region’s future electricity needs.
Interested parties in this engagement initiative include but are not limited to:
Peterborough to Kingston Technical Working Group - A Technical Working Group is led by the IESO and consists of the transmitter (Hydro One Networks Inc.) and the LDCs in the region including Hydro One Distribution, Eastern Ontario Power Inc., Elexicon Energy Inc., Lakefront Utilities Inc., Utilities Kingston. The group will use this regional planning engagement initiative to incorporate input while developing the IRRP.
All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.
Also see the regional planning webpage for Peterborough to Kingston
Date | Materials | Expected Actions |
---|---|---|
October 2, 2025 |
Deadline for public comment on Public Webinar #1 |
All feedback to be posted |
September 11, 2025 |
Public Webinar #1: Regional Electricity Planning (Forecasting) |
|
April 28, 2025 |
Peterborough to Kingston Scoping Assessment Outcome Report posted |
|
April 15, 2025 |
Deadline for public comment on Scoping Assessment Feedback received: |
All feedback posted |
April 2, 2025 |
Scoping Assessment Outcome Report |
Date | Materials | Expected Actions |
---|---|---|
November 5, 2021 |
Posted
|
|
October 19, 2021 |
Feedback on webinar #3 due |
Feedback to be posted |
September 28, 2021 10:00 a.m. |
Public Webinar #3 Overview of IRRP and recommendations, including details on evaluation of alternatives |
Seek input on IRRP recommendations |
September 1, 2021 |
Posted |
|
August 18, 2021 |
Feedback on webinar #2 due |
Feedback to be posted |
July 28, 2021 |
Public webinar #2
Outline of next steps, timelines and considerations for broader engagement |
Seek input on options screening and range of potential solutions to be examined |
May 11, 2021 |
Posted |
|
April 8, 2021 |
Feedback on public webinar #1 due |
Feedback will be posted and responded to |
March 25, 2021,
|
Public webinar #1
|
Seek input on draft engagement plan, electricity demand forecast and preliminary needs identified |
Q3 2020 |
Posted |
|
May 5, 2020 |
Posted |
|
April 30, 2020 |
Feedback due on draft Scoping Assessment |
|
April 16, 2020 |
Public Webinar #1
|
Seek input on draft Scoping Assessment |
April 2, 2020 |
Draft Peterborough-Kingston Region Scoping Assessment Outcome Report |
Draft posted for public comment |