Medium-Term RFP

Resource Acquisition

The Medium-Term Request for Proposals (RFP) is an initiative by the Independent Electricity System Operator (IESO) aimed at securing existing energy resources with expiring contracts to ensure the continued reliability and cost-effectiveness of Ontario’s electricity system.

By conducting Medium-Term RFPs every two to three years, the IESO can respond to changing system needs, maintain a stable energy supply, and encourage competition and innovation in the market.

To date, the IESO has completed two Medium-Term RFPs, MT1 and MT2, with the third procurement, MT3, soon to begin.

Related Information

Resource Acquisition and Contracts

Medium-Term RFP

Long-Term RFP

Medium-Term 3 RFP (MT3)

Building on the success of MT1 and MT2, the third Medium-Term RFP (MT3) is focused on re-committing existing resources with contracts expiring in or before 2032. These resources are strategically positioned to address the energy and capacity needs that will emerge later this decade and into the early 2030s.

The MT3 RFP will include proposals evaluated solely on price, ensuring a cost-effective approach to meeting Ontario’s future energy requirements.

The Schedule of Activities, upcoming engagement sessions, presentation materials, feedback forms, etc. would then sit directly under the MT3 section so stakeholders can quickly find the information associated with the active procurement.

Schedule of Activities

Date Engagement Activity Expected Actions

October 16, 2026

Engagement Webinar

The IESO will introduce the high-level design for the upcoming MT3 RFP and outline key procurement milestones and timelines.

Register

This webinar is being presented during the IESO's October stakeholder engagement sessions, see full agenda for more information.

Previous Medium-Term RFPs

Medium-Term 2 RFP (MT2)

The second Medium-Term RFP (MT2) was held in 2024 and consisted of two separate streams: the Energy Stream (MT2(e)) and the Capacity Stream (MT2(c)). Through MT2, the IESO executed contracts with 27 Selected Proponents, totalling 3,001.11 MW of Maximum Contract Capacity.

Schedule of Activities

Date Engagement Activity Expected Actions

November 14, 2024

Feedback due following the November 7th webinar.

Feedback Received:

December 10, 2024: IESO Response to Feedback

 

November 7, 2024

Medium-Term 2 RFP Documents – Q&A Webinar

The IESO will be holding a Q&A webinar on November 7 to address outstanding technical questions related to the latest MT2 RFP documents. No new material will be presented, and IESO’s legal team will be available for contractual inquiries.

Recorded Presentation

September 27, 2024

Feedback due following the September 12 webinar.

Feedback Received:

November 5, 2024: IESO Response to Feedback

 

September 12, 2024

Public Engagement Session

Recorded Presentation

August 27, 2024

 

August 19, 2024

 
Medium-Term 1 RFP (MT1)

The first Medium-Term RFP (MT1) was held in 2021 and resulted in the IESO entering into contracts for more than 700 MW of capacity from one wind facility and four natural gas facilities.

Schedule of Activities

Date Engagement Activity Expected Actions

August 23, 2022

Notification to all Proponents and announcement of Selected Proposals

April 28, 2022

Proposal submission deadline

April 21, 2022

IESO's deadline for issuing Addenda to MT I RFP and MTC I Contract, if any

April 14, 2022

MT I RFP Addenda #3 posted

April 4, 2022

MT I RFP Addenda #2 posted

March 25, 2022

IESO's deadline for responding to the Proponents confirming their status as a Qualified Applicant and their respective Monthly Qualified Capacity

February 22, 2022

Proponent's deadline for MT I RFP Registration

February 16, 2022

MT I RFP Addenda #1 posted

February 14, 2022

Proponent's deadline for submitting questions and comments

Question and Comment Form

January 31, 2022

MT I RFP Registration period opens

Final MT I RFP and MTC I Contract posted

Final MT I RFP Prescribed Forms posted

Updated MT I RFP Qualified Capacity Guidance document posted

Updated MT I RFP FAQ document posted

MT I RFP Question and Comment Form posted

January 7, 2022

MT I RFP FAQ Document posted

MT I RFP Draft Prescribed Forms posted

December 10, 2021

Deadline for questions and comments on the draft MT I RFP and draft MTC I Contract to be sent to the IESO

December 7, 2021

Webinar to discuss and address questions regarding the draft MT I RFP and MTC I Contract

Presentation

Recorded Presentation

November 25, 2021

Webinar to walk through and engage on the details of the draft MTC I Contract

Presentation

Recorded Presentation

November 24, 2021

Draft MT I RFP posted

Draft MTC I Contract posted

November 16, 2021

Webinar to walk through and engage on the details of the draft MT I RFP

Presentation 

Recorded Presentation

November 2, 2021

Draft MT I RFP posted