Forecasting and Planning
Regional electricity planning has commenced for the Barrie/Innisfil sub-region. This engagement initiative will provide interested parties with an opportunity to offer input for consideration as the process is underway on the development of an Integrated Regional Resource Plan (IRRP) anticipated to be complete in Q2 2022.
Regional electricity plans take a 20-year outlook on every region in the province. The planning process provides an opportunity for communities to tell the IESO about anticipated needs and priorities and to contribute to the development of the options for meeting this region’s future electricity needs.
All interested parties are invited to participate in this engagement initiative and may include but are not limited to:
Additional details on the IESO’s plans to engage with communities and interested parties throughout this process will be posted as part of a draft engagement plan, that will be open to public comment before finalizing by early Q4 2021.
Barrie/Innisfil Technical Working Group- A Technical Working Group consisting of the LDCs in the region (listed above), the local transmitter, Hydro One Networks and the IESO will use this regional planning engagement initiative to consider input that will identify and meet local electricity needs.
All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.
Also see the regional planning webpage for Barrie/Innisfil
Date | Materials | Expected Actions |
---|---|---|
June 24, 2022 |
South Georgian Bay/Muskoka Integrated Regional Resource Plan Appendices Posted |
|
June 17, 2022 |
Posted |
|
May 26, 2022 |
Posted |
|
May 3, 2022 |
Feedback on webinar #3 due No feedback received. |
Feedback to be posted |
April 6, 2022 2:00 p.m. |
Public Webinar #3 Overview of IRRP and recommendations, including details on evaluation of alternatives |
|
January 20, 2022 |
Posted |
|
December 30, 2021 |
Feedback on webinar #2 due |
Feedback to be posted |
December 9, 2021 |
Public webinar #2
Outline of next steps, timelines and considerations for broader engagement |
Seek input on options screening and range of potential solutions to be examined |
October 14, 2021 |
Posted |
|
September 30, 2021 |
Feedback due on public webinar #1 |
Feedback to be posted |
September 9, 2021 10:00 a.m. |
Public Webinar #1
|
Seek input on draft engagement plan, electricity demand forecast and preliminary needs identified |