The IESO is responsible for communicating to market participants about new or amended reliability standards and criteria, which may be subject to the Ontario Energy Board's (OEB) review. The OEB or any person may make an application for review of a reliability standard within the time prescribed as in Sections 36.2 (3) and 36.2 (4) of the Electricity Act, 1998 and Section 2. of Ontario Regulation 214/08 Reliability Standards as follows:

  • Date Posted: New or amended reliability standard are posted on the IESO’s website within seven days of being notified by the standards authority (NERC or NPCC).
  • Last Date to Request an OEB Review: There is a 21-day window from posting for any market participant, including the IESO, to apply to the OEB for review of the reliability standard.
  • Last Date for OEB to Initiate Its Own Review: Within 120 days from posting the OEB can initiate its own review.
    • If a review is initiated the OEB has the authority to stop the standard from applying in Ontario and to refer it back to the standards authority.
  • If there is no review, the standard comes into effect under the Market Rules on the enforcement date of the reliability standard.

Proposed new or amended reliability standards

The table below provides a summary of proposed new or amended reliability standards and criteria currently subject to the OEB's review process. To request a copy of the summaries below, please contact customer.relations@ieso.ca with a link to the web page along with the summary description and posting date, and advise whether it needs to be provided in an accessible format. Please allow a minimum of one business day for a response.

Date of Notice
of Filing
Date Posted Last Date to Request an OEB Review Summary of Proposed New or Amended
NERC Standard or NPCC Criteria
Last Date for OEB to Initiate Its Own Review Link to Petition for Approval of Proposed Reliability Standard Link to the Approved Standard

2025/01/10

2025/01/13

2025/02/03

Summary of Proposed Reliability Standards: BAL-007-1 AND TOP-003-7

May 13, 2025

Petition for Approval of Proposed Reliability Standards BAL-007-1 and TOP-003-7

BAL-007-1

TOP-003-7

2024/12/20

2024/12/23

2025/01/13

Summary of Proposed Reliability Standard CIP-002-8

April 22, 2025

Petition for Approval of Proposed Reliability Standard CIP-002-8

 

2024/12/20

2024/12/23

2025/01/13

Summary of Proposed Reliability Standard CIP-003-11

April 22, 2025

Petition for Approval of Proposed Reliability Standard CIP-003-11

 

2024/12/20

2024/12/20

2025/01/10

Summary of Proposed Reliability Standards: TPL-008-1

April 19, 2025

Petition for Approval of Proposed Reliability Standard TPL-008-1

TPL-008-1

2024/11/04

2024/11/12

2024/12/03

Summary of Proposed Reliability Standards PRC-028-1 and PRC-002-5

March 11, 2025

Petition for Approval of IBR Disturbance Monitoring Standards

PRC-028-1

PRC-002-5

2024/11/04

2024/11/12

2024/12/03

Summary of Proposed Reliability Standard PRC-030-1

March 11, 2025

Petition for Approval of proposed Reliability Standard PRC-030-1

PRC-030-1

2024/11/04

2024/11/12

2024/12/03

Summary of Proposed Reliability Standards PRC-029-1 and PRC-024-4

March 11, 2025

Petition for Approval of Proposed Reliability Standards PRC-024-4 and PRC-029-1


2024/08/15

2024/08/19

2024/09/09

Summary of Proposed Eleven NERC CIP Reliability Standards

December 17, 2024

NERC Petition for Approval of Critical Infrastructure Protection Reliability Standards

 

2024/07/03

2024/07/17

2024/08/07

IESO's Summary of Proposed NPCC Criteria Directory #1

November 14, 2024

N.A.

N.A.

2024/07/03

2024/07/08

2024/07/29

IESO's briefing to the OEB regarding proposed NERC standard CIP-015-1

November 05, 2024

Petition for Approval of Proposed Reliability Standard CIP-015-1

 

2024/01/31

2024/03/21

2024/04/11

IESO's briefing to the OEB regarding proposed NERC standard CIP-012-2

July 19, 2024

Petition for Approval of Proposed Reliability Standard CIP-012-2

CIP-012-2

2024/02/29

2024/03/04

2024/03/25

IESO's briefing to the OEB regarding proposed NERC standard EOP-012-2

July 2, 2024

Petition for Approval of Reliability Standard EOP-012-2 and Request for Expedited Action

EOP-012-2

2023/12/12

2023/12/13

2023/12/31

IESO's briefing to the OEB regarding proposed NERC standard PRC-002-4

April 11, 2024

Petition for Approval of Proposed Reliability Standard PRC-002-4

PRC-002-4

2023/11/10

2023/11/15

2023/12/06

IESO's briefing to the OEB regarding proposed NERC standards EOP-011-4 and TOP-002-5

March 14, 2024

Petition for Approval of Proposed Reliability Standards EOP-011-4 and TOP-002-5 and Request for Expedited Action

EOP-011-4
TOP-002-5

2023/11/03

2023/11/08

2023/11/30

IESO's briefing to the OEB regarding proposed NERC standard PRC-023-6

March 7, 2024

Amended Petition for Approval of Proposed Reliability Standard PRC-023-6

PRC-023-6

2023/10/30

2023/11/02

2023/11/23

IESO's briefing to the OEB regarding proposed NERC standards IRO-010-5 TOP-003-6.1

March 1, 2024

Petition for Approval of Proposed Reliability Standards IRO-010-5 and TOP-003-6.1

IRO-010-5
TOP-003-6.1

2023/02/02

2023/03/20

2023/03/27

IESO’s briefing to the OEB regarding proposed NPCC Criteria Directory #8 (002)

July 18, 2023

N.A.

N.A.

2023/01/05

2023/01/05

2023/01/26

IESO's briefing to the OEB regarding proposed NERC standards CIP-003-9

May 5, 2023

Petition for Approval of Proposed Reliability Standard CIP-003-9

CIP-003-9

2022/12/09

2022/12/09

2022/12/31

IESO's briefing to the OEB regarding proposed NERC standards EOP-011-3 and EOP-012-1

April 8, 2023

Petition for Approval of Proposed Reliability Standards EOP-011-3 and EOP-012-1

EOP-012-1

2022/06/14

2022/06/21

2022/07/11

IESO's briefing to the OEB regarding proposed NERC standards FAC-001-4 and FAC-002-4

October 19, 2022

Petition for FAC-001-4 and FAC-002-4

FAC-001-4
FAC-002-4


See Closed OEB Reviews.