Wrap-Up Meeting for Cutover Test
April 3, 2025
The IESO conducted a cutover test with market participants from March 31 to April 2 to verify that both internal and external participants can follow and execute the cutover sequence of activities in the prescribed time, as outlined in Table 3-1 of the MRP Readiness Plan for the Market Renewal launch.
The IESO is hosting a wrap-up meeting on Friday, April 11 from 2:00 p.m. to 3:30 p.m. to provide key takeaways from the test and a second walkthrough of launch activities to prepare for the cutover.