IESO Invites Comments on an Exemption to the Market Rules
October 3, 2024
Algoma Steel Inc. has applied for exemption from Market Rule Chapter 9 s.2.4A.2., requesting that generation from their Lake Superior self-scheduling generation facilities may be used to offset the load from their new electric arc furnace non-dispatchable load facilities. If approved, the electric arc furnace and Lake Superior generation facilities may be settled collectively on a ‘net’ basis.
The exemption information and the IESO’s recommendation are posted for third-party comment. Comments may be sent to exemptions@ieso.ca by October 11, 2024.