The IESO is conducting a review of its generation guarantee programs including elements of the Real-Time Generation Cost Guarantee (RT-GCG) and Day-Ahead Production Cost Guarantee (DA-PCG). The review will consider the effectiveness of aspects of these guarantee programs from a cost, as well as an operational effectiveness and economic efficiency perspective.
The goal of this stakeholder engagement initiative is to gather feedback from stakeholders on the approach of this review, as well as the recommendations and implementation of any changes identified through the review.
This initiative is likely to be of interest to all wholesale market participants and stakeholder groups. Generators and traders will have an interest given the direct impact the cost guarantees may have on their day-to-day operations. Consumers will also have an interest as they pay for the program costs.
This Stakeholder Engagement Plan has been developed to define the opportunity for stakeholder involvement.
Stakeholder Engagement Plan (Draft)
Stakeholder Engagement Plan (Draft, June 24, 2013)
Stakeholder Engagement Plan (Final)
Documents referenced on this page, but not posted, can be obtained by contacting customer.relations@ieso.ca with a link to the web page that lists the document and advise whether it needs to be provided in an accessible format. Please allow a minimum of one business day for a response.
Date |
Activities |
Expected Actions |
---|---|---|
January 2017 |
Engagement completed |
|
November 24, 2016 |
||
September 6, 2016 |
SE-111 Update
|
|
June 30, 2016 |
Update - Ramp Down CSMC
|
|
May 19, 2016 |
Update - Review of Generation Guarantee Programs (SE-111)
|
|
October 9, 2015 |
Update – Review of Generation Guarantee Programs
|
|
August 21, 2015 |
Update – Review of Generation Guarantee Programs
|
|
April 29, 2015 |
|
|
February 23, 2015 |
|
|
February 5, 2015 |
Stakeholders to provide written feedback on the material presented at Stakeholder Session 6 Stakeholder Feedback
|
|
January 22, 2015 Minutes |
Stakeholder Session #6 – Webinar to review and respond to the feedback from the November 27th meeting and to present a revised proposed solution to address the issue of self-induced CSMC during ramp down.
|
|
December 12, 2014 |
Stakeholders to provide written feedback on the material presented at Stakeholder Session 5 Stakeholder Feedback
|
|
November 27, 2014 Minutes (Draft) |
Stakeholder Session #5 – Webinar to review and respond to the feedback submitted by stakeholders on the proposed options to address the issue of self-induced CMSC during ramp-down
|
|
October 10, 2014 |
Stakeholders to provide written feedback on the material presented at Stakeholder Session 4 Stakeholder Feedback
|
|
September 26, 2014 Agenda
Minutes
|
Stakeholder Session #4 - to discuss final recommendations
|
Dialogue - presentation to stakeholders |
March 31, 2014 Agenda Minutes |
Stakeholder Session #3 - to discuss further analysis findings and preliminary recommendations
|
Dialogue - presentation to stakeholders |
January 17, 2104 |
IESO Response to Stakeholder Feedback |
|
November 21, 2013 |
Stakeholders to provide written feedback on the material presented at Stakeholder Session 2 Stakeholder Feedback
|
Feedback due from Stakeholders |
November 7, 2013 Agenda Minutes |
Stakeholder Session #2 - to discuss findings of materiality analysis, possible solutions and proposed 'benefits' analysis
|
Dialogue - presentation to stakeholders |
Q3/Q4 |
IESO Analysis |
|
August 22, 2013 |
|
|
August 8, 2013 |
Stakeholder Feedback
|
Stakeholders to provide written feedback |
July 18, 2013 Agenda Minutes |
Stakeholder Session #1 - to discuss comments, IESO responses and proposed materiality analysis
|
Dialogue - presentation to stakeholders |
July 11, 2013 |
IESO Response to Stakeholder Feedback - revised |
|
June 27, 2013 |
Deadline for feedback from stakeholders on Stakeholder Engagement Plan and Discussion Paper in writing or through Stakeholder Feedback
|
Feedback due from Stakeholders |
June 7, 2013 |
Stakeholders to advise if further clarification is required on Stakeholder Engagement Plan and Discussion Paper through an information webinar |
Stakeholders to submit questions for clarification |
May 30, 2013 |
Post and communicate Stakeholder Engagement Plan
|
Stakeholders to provide feedback in writing or through available survey |
Real-time Generation Cost Guarantee
Quick Takes - Real Time Generation Cost Guarantee
Market Manual 5.5: Physical Markets Settlement Statements (section 1.6.4)
Day Ahead Commitment Process
Market Manual 9.5: Settlement for the Day-Ahead Commitment Process
Guide to the Day-Ahead Commitment Process (DACP)