Regional Electricity Planning - Kitchener-Waterloo-Cambridge-Guelph

Documents referenced on this page, but not posted, can be obtained by contacting engagement@ieso.ca with a link to the web page that lists the document and advise whether it needs to be provided in an accessible format. Please allow a minimum of one business day for a response.

A new regional planning cycle is underway for the Kitchener-Waterloo-Cambridge-Guelph (KWCG) region. The first cycle of regional planning for the region began in 2010 and was completed in April 2015 with the release of an Integrated Regional Resource Plan (IRRP). The next IRRP for the region is anticipated to be completed in Q1 2021.

This engagement initiative will provide interested parties with an opportunity to offer input for consideration into the development of the IRRP. Interested parties include but are not limited to:

  • Municipalities of Kitchener, Waterloo, Cambridge and Guelph, as well as portions of Perth, Oxford and Wellington counties and the townships of Wellesley, Woolwich, Wilmot, North Dumfries, and the Region of Waterloo
  • Indigenous communities including the Grand River Métis Council, Six Nations of the Grand River and Mississaugas of the New Credit
  • Local distribution companies (LDCs) who serve the community including Alectra Utilities (Guelph), Energy+, Halton Hills Hydro, Kitchener-Wilmot Hydro, Waterloo North Hydro, Centre Wellington Hydro, Wellington North Power, Milton Hydro and Halton Hills Hydro
  • Transmitters
  • Consumers and service providers for the area

All interested parties are invited to participate in this engagement initiative.

Additional details on the IESO’s plans to engage communities and interested parties throughout the process can be found in the engagement plan.

All comments and enquiries in this engagement initiative can be directed to engagement@ieso.ca.

KWCG Technical Working Group - A Technical Working Group consisting of the seven local distribution companies in the region, the local transmitter and the IESO will use this regional planning engagement initiative to consider input to develop the IRRP for the KWCG region.


Related Information

Final Kitchener-Waterloo-Cambridge-Guelph Region Scoping Assessment Outcome Report

Hydro One KWCG Region Needs Assessment Report -December 2018

2015 KWCG Area IRRP

2015 KWCG Area IRRP - Appendices

Backgrounder

Kitchener-Waterloo-Cambridge-Guelph IRRP Webinar Archive

Terms of Reference

Terms of Reference Addendum

See also the regional planning webpage for KWCG.

Schedule of Activities

Date  Materials Expected Actions 

April 2021

Finalize KWCG IRRP

  • Post final report
  • IESO responses to feedback received on draft recommendations posted
  • Close engagement
  • Conduct survey on engagement process

April 1, 2021

Feedback on public webinar #2 due

Feedback form

Sustainable Waterloo Region

 

March 18, 2021

Public webinar #2

Communication

Presentation

  • Overview of options examined and IRRP and recommendations, including details on evaluation of alternatives
  • Discuss considerations for communities and interested parties to consider in their medium- to long-term planning

Recorded Presentation

Seek input on further discussions needed to initiate near-term projects

September 2020

Status update

  • Communication
 

January 29, 2020

IESO responses to feedback received

Response posted

December 19, 2019

Feedback on public webinar #1 due

  • City of Waterloo
  • Sandra Bray

Feedback posted

December 5, 2019

Public webinar #1

Presentation

  • Overview of the regional electricity planning process in Ontario
  • Update on planning activities underway

Summary of preliminary regional demand forecast and needs and draft engagement plan

Register for webinar: https://www.meetview.com/ieso20191205/

Presentation and recorded webinar posted

Seek input on draft engagement plan, electricity demand forecast and preliminary needs identified

November 21, 2019

Engagement plan posted for review and comment

Posted

May 9, 2019

Final KWCG Scoping Assessment Outcome Report and Terms of Reference

  • Communication

Final version posted following a two-week comment period

May 9, 2019

KWCG Scoping Assessment Outcome Report and Terms of Reference – Responses to Public Comments

Posted

April 25, 2019

Deadline for public comment on draft KWCG Scoping Assessment Outcome Report and Terms of Reference

  • Region of Waterloo

Posted

April 11, 2019

Draft KWCG Scoping Assessment Outcome Report and Terms of Reference

  • Communication

Draft posted for public comment