Integrated Regional Resource Plan - Hamilton Sub-Region
A new regional planning cycle is underway for the Hamilton sub-region, and an Integrated Regional Resource Plan (IRRP) has been completed following a community engagement initiative.
This engagement initiative provided interested parties with an opportunity to offer input for consideration into the development of the IRRP.
Interested parties included but were not limited to:
- Municipalities including the City of Hamilton, which includes the communities of Hamilton, Flamborough, Dundas, Ancaster, Glanbrook, Binbrook, Waterdown, and Stoney Creek
- Indigenous Communities including the Mississaugas of the New Credit and Six Nations of the Grand River
- Local distribution companies who serve the community including Alectra Utilities and Hydro One
- Transmitters
- Consumers and services providers for the area
All interested parties are invited to participate in this engagement initiative.
Hamilton Technical Working Group - A Technical Working Group consisting of the local distribution companies in the region, the local transmitter and the IESO will use this regional planning engagement initiative to consider input that will identify and meet local electricity needs. The Technical Working Group consists of representatives from the LDC in the area – Alectra Utilities, as well as the transmitter Hydro One Networks Inc., and the IESO.
All comments and enquiries in this engagement initiative can be directed to communityengagement@ieso.ca.
Related Information
Hydro One’s Needs Assessment – May 2017
See also Hamilton sub-regional planning webpage
Schedule of Activities
Date |
Materials |
Expected Actions |
---|---|---|
February 25, 2019 |
IESO appreciates the participation in this engagement initiative. Subscribe to receive updates for this planning region (“Burlington to Nanticoke”) here |
Engagement closed |
February 25, 2019 |
Final version posted following a two-week comment period |
|
February 4, 2019 |
|
The comment period to submit feedback on the draft Hamilton IRRP is open until February 12, 2019. Questions or feedback can be submitted to communityengagement@ieso.ca. Submissions will be posted and responded to on the IESO website as part of the posting of the Final Hamilton IRRP at the end of February. |
September 2017 |
Final version posted following a two-week comment period |
|
August 2017 |
Draft Burlington to Nanticoke Scoping Assessment Outcome Report |
Posted for public comment |