The IESO has formed this working group to get feedback on the MPI/API replacement refresh project. Stakeholders are asked to give input on matters relating to the redesign, transition, implementation schedule and key milestones of the project.
At the conclusion of the working group, the IESO will publish a final project plan with the implementation timeline.
Terms of Reference (Draft)
Documents referenced on this page, but not posted, can be obtained by contacting customer.relations@ieso.ca with a link to the web page that lists the document and advise whether it needs to be provided in an accessible format. Please allow a minimum of one business day for a response.
Date Agenda Minutes |
Activities | Expected Actions |
---|---|---|
October 7, 2016 |
MPI/API Replacement Working Group now complete
|
|
August 3, 2016 |
EMI Training webinar
|
|
July 20, 2016 |
EMI Training webinar
|
|
July 18, 2016 |
New Sandbox System for Bid and Offer Submissions
|
|
June 27, 2016 |
EMI Training Webinar |
|
June 17, 2016 |
Changes to MIM IDK API Accounts Coming Soon
|
|
June 3, 2016 |
Webinar
|
|
May 24, 2016 |
Important Changes to the Bid and Offer Submission Process
|
|
May 9, 2016 |
EMI Market Trial
The user guides that were posted here are now available on the Marketplace Training page. |
|
April 27, 2016 |
EMI Market Trials – Postponed
|
|
April 25, 2016 |
EMI Market Trial
|
|
April 22, 2016 |
EMI Market Trials
|
|
February 24, 2016 |
Webinar
|
|
January 4, 2016 |
MIM API Market Trial - Wrap Up
|
|
December 9, 2015 |
API Market Trial - touchpoint
|
|
November 25, 2015 |
MIM 3 week Market Trial begins (ends December 16, 2015) |
|
November 24, 2015 |
Webinar to review the MIM Market Trial which will take place to test the IDK and API accounts
|
|
November 18, 2015 |
|
|
November 12, 2015 |
|
|
October 15, 2015 |
Webinar to provide an update on the project progress, market place testing and next steps.
|
|
April 17, 2015 |
Deadline for written input from stakeholders on EMI RTEM mock-up screens
|
|
March 30, 2015 |
Unexpected Actions – Working group meeting
|
|
March 19, 2015 |
IESO Response to Stakeholder Feedback |
|
January 7, 2015 |
|
Working Group to provide written feedback by January 14, 2015 |
December 10, 2014 |
|
Working Group to provide written feedback by December 30, 2014 |
October 23, 2014 |
IESO Response to Stakeholder Feedback |
|
October 9, 2014 |
Stakeholder feedback requested on the web service design |
|
September 25, 2014
|
Meeting to provide an update on the API web services design
|
Working Group Meeting
|
September 16, 2014 |
Stakeholder feedback requested on Access Control in Online IESO
|
|
August 20, 2014 |
IESO Response to Stakeholder Feedback |
|
July 18, 2014 |
Deadline for Stakeholder Feedback
|
Working Group to provide written feedback |
June 27, 2014 |
Meeting to present refined proposal (2nd draft) based on stakeholder feedback
|
Working Group meeting |
June 17, 2014 |
IESO Response to Stakeholder Feedback |
|
May 19, 2014 |
Stakeholder Feedback |
Working Group to provide written feedback |
April 28, 2014 |
Initial meeting to present proposed changes to MPI/API solution and preliminary schedule
|
Working Group meeting |
March 27, 2014 |
Communicate in IESO Bulletin to request for working group volunteers |
Stakeholders to provide written feedback by April 14, 2014 |