Enhanced Day-Ahead Commitment (EDAC) - I.T. Build (SE-87)
The overall Enhanced Day-Ahead Commitment (EDAC) project is comprised of the following three phases.
1. Initiation and Design Phase
2. Build and Test Phase
3. Adoption and GO-LIVE Phase (including Project Closure)
For the Initiation and Design Phase, Market Design was managed primarily through stakeholder engagement plan SE-21, and the detailed design was the focus of stakeholder engagement plan EDAC Detailed Design (SE-73). The market facing elements of the I.T. Build portion of the Build and Test Phase will be the subject of this stakeholder engagement plan.
The objective of this plan is to provide affected stakeholders with the opportunity to identify operational and settlement issues with respect to EDAC market facing systems and reports, in order to minimize potential adverse impacts.
This initiative will involve market participants that enter bids and offers into the market as they will be directly affected by the implementation of EDAC - including generators, importers and exporters.
Stakeholder Engagement Plan
Terms of Reference
Working Group Membership
For more information on this stakeholder initiative, email
stakeholder.engagement@ieso.ca.
Proposed Activities
| Date |
Activity |
Expected Actions |
| October 13, 2011 |
IESO Enhanced Day Ahead Commitment Successfully Launched |
|
| October 7, 2011 |
EDAC Settlements external review report |
Reference |
| February 25, 2011 |
RTEM Three-Part Offer Template Technical Interface Updated (Removed reference to Restricted Window)
Note: Template for OR offers did not change for EDAC |
|
| February 15, 2011 |
IESO Developers Kit (IDK) Implementation Manual IMO_MAN_0023_v11.1
Market Information Management Application Interface (MIM API) SIDK v3.3.exe |
|
| December 21, 2010 |
DACP Valid DGD Technical Interface Updated
RTEM Three-Part Offer Template Technical Interface Updated |
DGD(txt) Updated
DACP RTEM BidNormalE(txt) Updated
DACP RTEM BidStandingE(txt) Updated |
| July 2010 |
Public Reports |
Stakeholder Review |
| June 10, 2010 |
Review Report Specifications with Technical Working Group |
Dialogue – stakeholder input |
| April 2010 |
Review Technical Specifications with Technical Working Group
• Communication update |
Dialogue – stakeholder input |
| March 24, 2010 |
Second Technical Working Group meeting or conference call to review MIM changes |
Dialogue – stakeholder input |
February 12, 2010
Agenda |
First Technical Working Group meeting. Focus on high level description of market facing system and report changes
• Technology Changes
• Solution Changes to Enable the EDAC Project
• EDAC Stage 4 - IT Design Build |
Dialogue – stakeholder input Stakeholders to provide written feedback by February 26, 2010 |
| February 5, 2010 |
No comments received on stakeholder engagement plan. |
Stakeholders to provide written feedback |
| January 28, 2010 |
Post and communicate stakeholder engagement plan for comments and solicit representative for the support groups |
Stakeholders to provide written feedback by February 4, 2010 |