A new regional planning cycle is underway for the Windsor-Essex region. The first cycle of regional planning for the region began in 2010 and was completed in April 2015 with the release of an Integrated Regional Resource Plan (IRRP). The next IRRP for the region is anticipated to be completed in Q3 2019.

This engagement initiative will provide interested parties with an opportunity to offer input for consideration into the development of the IRRP. Interested parties include but are not limited to:

  • Municipalities including the City of Windsor, Town of Amherstberg, Town of Essex, Town of Kingsville, Town of Lakeshore, Town of LaSalle, Municipality of Leamington, Town of Tecumseh, and the western portion of the Municipality of Chatham-Kent and the Township of Pelee Island
  • Indigenous Communities including the Caldwell First Nation
  • Local distribution companies who serve the community including EnWin Utilities, Essex Powerlines, E.L.K. Energy, Entegrus and Hydro One
  • Transmitters
  • Consumers and service providers for the area

All interested parties are invited to participate in this engagement initiative.

Windsor-Essex Working Group - A Technical Working Group consisting of the local distribution companies in the region, the local transmitter and the IESO will use this regional planning engagement initiative to consider input that will identify and meet local electricity needs. The Working Group consists of representatives from the five LDCs in the area - EnWin Utilities, Essex Powerlines Corporation, E.L.K. Energy Inc., Entegrus Powerlines Inc., the transmitter Hydro One Networks Inc., and the IESO.

All comments and enquiries in this engagement initiative can be directed to communityengagement@ieso.ca.

 

Schedule of Activities

Date

Materials

Expected Actions

Q3 2019

Final IRRP

Posted along with responses to feedback

August 2019

Webinar to seek input on proposed recommendations for IRRP

 

July 2019 

IESO to respond to feedback

IESO response posted

June 14, 2019

Feedback due

All feedback posted

May 30, 2019

Meeting Summary

 

Kingsville-Leamington LAC meeting #3: In person

Present and seek input on draft demand-side recommendations for Kingsville-Leamington area

           

May 10, 2019

Engagement Webinar #2 – present:

  • Presentation
  • Overview of the region’s electricity needs
  • Seek input for consideration on potential solutions

Feedback due June 14, 2019

               

February 27, 2019
10:00 a.m. – 2:30 p.m.
Best Western Plus, Leamington

Agenda 

Meeting Summary

 LAC Meeting #2: In person

Post meeting materials and summaries

     

January 31, 2019

 

December 4, 2018

Agenda

Meeting Summary

First meeting of the Kingsville-Leamington Local Advisory Committee

 

November 30, 2018

IESO to respond to feedback on draft engagement plan and terms of reference

Announcement of Leamington-Kingsville Local Advisory Committee

 

Post final engagement plan and final terms of reference

Post membership of Local Advisory Committee

November 23, 2018

Feedback due on draft engagement plan; terms of reference

Call for nominations closed

Post feedback

November 15, 2018

 

Engagement Webinar #1 – Present:

  • Presentation
  • Overview of Windsor-Essex IRRP engagement initiative:                
  • Draft Windsor-Essex Engagement Plan                                            
  • Draft Kingsville-Leamington Local Advisory Committee Terms of Reference

Recorded Presentation

The comment period to submit feedback on the draft engagement materials closed on November 23, 2018 and materials have now been finalized.  

                       

November 1, 2018

Launch IRRP Windsor-Essex engagement initiative

Seek input on draft engagement plan and terms of reference for Advisory Committee

 

 March 2018

 

Windsor-Essex Scoping Assessment Outcome Report and Terms of Reference

Final version was posted following a two week comment period

 

 January 2018

 

2018 Windsor-Essex Scoping Assessment Outcome Report - Responses to Public Comments

Responses were posted to IESO website